Typical Cross Section of Bridge

(Looking East)

This cross-section of the bridge is viewed coming into downtown, looking east. The north side of the bridge has an 8’ sidewalk and the south side a 5’ sidewalk. The bicycles will share the lane with traffic coming into town (the lane the truck is in). Leaving town, bicycles will have their own 5’ bike lane on the asphalt.


Project Planview

The Woodin Avenue Bridge Project wraps together many efforts, including bridge restoration, safety improvements, and upgrading utilities to accommodate future needs. The project also makes the area more inviting, widening 1,900 feet of sidewalks, adding 1,200 feet of new bike lanes, enhancing streetscapes, and adding the new Woodin Avenue Landing Park.